|
Resolved:
(Moved: Councillors Malicki/Pettett)
THAT the Council, as the consent authority, grant deferred
development consent to DA0552/14 for the construction of 13 small lot houses
and Community Title subdivision into 14 lots, being 13 residential Torrens
title lots and 1 community Lot for the private road, at 90-92 Eton Road,
Lindfield (formerly 100 Eton Road), for a period of two (2) years from the
date on which the consent becomes operable.
SCHEDULE A: Deferred Commencement - Terms to be satisfied prior to
the consent becoming operable
The
following deferred commencement terms must be complied with to the
satisfaction of Council within 24 months of the date of issue of this
deferred commencement consent:
Approval for relocation of Council pipe and easement
In order for the consent to become operable;
(i) The applicant must
obtain a resolution from Ku-ring-gai Council, as the asset owner, that it
will consent to the relocation of the existing Council easement for drainage
and underground pipe.
(ii) A full hydraulic
design for the relocation of the pipe is to be prepared in accordance with
the requirements of Chapter 9 of Council’s DCP 47 Water Management and
submitted to Council with the relevant application and fees. The design must
be suitable for construction.
(iii) Council’s
resolution is required for the relocation of the pipe, extinguishment of the
existing easement and where required, the creation of a new easement.
Reason: To protect the environment and Council's assets.
Once the
consent becomes operable, the following conditions apply:
SCHEDULE B –
Conditions of Development Consent
Conditions that identify approved plans:
1. Approved architectural plans and
documentation (new development)
The development must be carried out in accordance with the
following plans and documentation listed below and endorsed with Council’s
stamp, except where amended by other conditions of this consent:
|
Plan no.
|
Drawn by
|
Dated
|
|
P5-DA01-100[2]
|
Batessmart
|
04.06.15
|
|
P5-DA02-101[2]
|
Batessmart
|
04.06.15
|
|
P5-DA05-001[1]
|
Batessmart
|
10.04.15
|
|
P5-DA05-002[1]
|
Batessmart
|
10.04.15
|
|
P5-DA05-003[1]
|
Batessmart
|
10.04.15
|
|
P5-DA05-004[1]
|
Batessmart
|
10.04.15
|
|
P5-DA05-005[1]
|
Batessmart
|
10.04.15
|
|
P5-DA05-006[1]
|
Batessmart
|
10.04.15
|
|
P5-DA05-007[1]
|
Batessmart
|
10.04.15
|
|
P5-DA05-008[1]
|
Batessmart
|
10.04.15
|
|
P5-DA05-009[1]
|
Batessmart
|
10.04.15
|
|
P5-DA05-010[1]
|
Batessmart
|
10.04.15
|
|
P5-DA05-011[1]
|
Batessmart
|
10.04.15
|
|
P5-DA05-012[1]
|
Batessmart
|
10.04.15
|
|
P5-DA05-013[1]
|
Batessmart
|
10.04.15
|
|
P5-DA07-001[2]
|
Batessmart
|
10.04.15
|
|
P5-DA07-002[2]
|
Batessmart
|
10.04.15
|
|
P5-DA07-100[1]
|
Batessmart
|
04.12.14
|
|
P5-DA07-101[1]
|
Batessmart
|
04.12.14
|
|
P5-DA07-102[1]
|
Batessmart
|
04.12.14
|
|
P5-DA07-103[1]
|
Batessmart
|
04.12.14
|
|
P5-DA07-104[1]
|
Batessmart
|
04.12.14
|
|
P5-DA07-105[1]
|
Batessmart
|
04.12.14
|
|
P5-DA07-106[1]
|
Batessmart
|
14.09.26
|
|
P5-DA07-107[1]
|
Batessmart
|
04.12.14
|
|
P5-DA07-108[1]
|
Batessmart
|
04.12.14
|
|
P5-DA07-109[1]
|
Batessmart
|
04.12.14
|
|
P5-DA08-002[1]
|
Batessmart
|
04.12.14
|
|
P5-DA08-003[1]
|
Batessmart
|
04.12.14
|
|
Materality Sheets 1
and 2
|
Batessmart
|
Undated
|
|
C101 Rev C
|
James Taylor and
Associates
|
07.04.15
|
|
C102 Rev B
|
James Taylor and
Associates
|
07.04.15
|
|
C104 Rev B
|
James Taylor and
Associates
|
07.04.15
|
|
C105 Rev C
|
James Taylor and
Associates
|
07.04.15
|
|
C106 Rev B
|
James Taylor and
Associates
|
07.04.15
|
|
C107 Rev A
|
James Taylor and
Associates
|
07.04.15
|
|
C201 Rev B
|
James Taylor and
Associates
|
07.04.15
|
|
DA-L-100 Rev 3
|
Turf
|
11/06/15
|
|
DA-L-300 Rev 3
|
Turf
|
11/06/15
|
|
DA-L-400 Rev 3
|
Turf
|
11/06/15
|
|
L-P5-DA-10
|
Turf
|
09/04/15
|
|
L-P5-DA-11
|
Turf
|
09/04/15
|
|
TDS-SK-001 Rev 1
|
Turf
|
02/04/15
|
|
Draft Precinct 5
subdivision plan
|
Peter William
Vandergraaf
|
03.06.2015
|
|
TMP01 Issue B Sheet 1
of 2
|
Naturally Trees
|
08/04/15
|
|
TMP01 Issue B Sheet 2
of 2
|
Naturally Trees
|
08/04/15
|
Reason: To ensure that the development is in accordance with the
determination.
2. Inconsistency between documents
In the event of any inconsistency between conditions of this
consent and the drawings/documents referred to above, the conditions of this
consent prevail.
Reason: To ensure that the development is in accordance with the
determination.
3. Approved landscape plans
Landscape works shall be carried out in accordance with the
following landscape plan(s), listed below and endorsed with Council’s stamp, except
where amended by other conditions of this consent:
|
Plan no.
|
Drawn by
|
Dated
|
|
DA-L-100 Rev B, DA-L-300 Rev B, A-L-400 Rev B, DA-L-500 Rev
B, L-P5-DA-10 Issue 2, L-P5-DA-11 Issue 2 TDS-SK-001 Rev 1
|
Turf
|
11/06/15 9/04/15 2/04/15
|
Reason: To ensure that the development is in
accordance with the determination.
4. Amendments to
approved plans
The approved plans
including architectural, landscaping and engineering shall be amended as
follows:
- The proposed sandstone retaining wall to the landscape
easement between the private open space of Precinct 5 and the
adjoining Asset Protection Zone is to follow the existing
contours to ensure compliance with maximum 1 metre height and avoid conflicts
with rock outcropping (5.7.5 Edgelea Urban
Design Guidelines February 2012).
Prior to the issue of the
Construction Certificate, the Principal Certifying Authority shall be
satisfied that the landscape plan has been amended are required by this
condition.
Note: An amended plan, prepared by a
landscape architect or qualified landscape designer shall be submitted to the
Certifying Authority.
Reason: To ensure the development is in accordance with the
determination
Conditions to be satisfied prior to demolition, excavation or
construction:
5. Asbestos works
All work involving asbestos products and materials, including
asbestos-cement- sheeting (ie. Fibro), must be carried out in accordance with
the guidelines for asbestos work published by WorkCover Authority of NSW.
Reason: To ensure public safety
6. Notice of commencement
At
least 48 hours prior to the commencement of any development (including
demolition, excavation, shoring or underpinning works), a notice of
commencement of building or subdivision work form and appointment of the
principal certifying authority form shall be submitted to Council.
Reason: Statutory
requirement.
7. Notification of builder’s details
Prior to the commencement of any
development or excavation works, the Principal Certifying Authority shall be
notified in writing of the name and contractor licence number of the
owner/builder intending to carry out the approved works.
Reason: Statutory
requirement.
8. Dilapidation survey and report (public infrastructure)
Prior to the commencement of any development or
excavation works on site, the Principal Certifying Authority shall be
satisfied that a dilapidation report on the visible and structural condition
of all structures of the following public infrastructure, has been completed
and submitted to Council:
Public
infrastructure
· Full road pavement, including kerb and gutter, of
Eton Road from Abingdon Road to the southern extremity of the subject site,
including the bus bay.
Tubbs
View, full road pavement.
The
report must be completed by a consulting structural/civil engineer.
Particular attention must be paid to accurately recording (both written and
photographic) existing damaged areas on the aforementioned infrastructure so
that Council is fully informed when assessing any damage to public
infrastructure caused as a result of the development.
The
developer may be held liable to any recent damage to public infrastructure in
the vicinity of the site, where such damage is not accurately recorded by the
requirements of this condition prior to the commencement of works.
Note: A written
acknowledgment from Council must be obtained (attesting to this condition
being appropriately satisfied) and submitted to the Principal Certifying
Authority prior to the commencement of any excavation works.
Reason: To record the
structural condition of public infrastructure before works commence.
9. Dilapidation survey and report (private
property)
Prior to the commencement of any demolition or
excavation works on site, the Principal Certifying Authority shall be
satisfied that a dilapidation report on the visible and structural condition
of all structures upon the following lands, has been completed and submitted
to Council:
|
Address
|
|
· 64 Abingdon Road.
|
|
· 10 Kimo Street (if
construction of dwelling has commenced).
|
|
|
The dilapidation report must include a photographic
survey of adjoining properties detailing their physical condition, both
internally and externally, including such items as walls ceilings, roof and
structural members. The report must be completed by a consulting
structural/geotechnical engineer as determined necessary by that professional
based on the excavations for the proposal and the recommendations of the
submitted geotechnical report.
In
the event that access for undertaking the dilapidation survey is denied by a
property owner, the applicant must demonstrate in writing to the satisfaction
of the Principal Certifying Authority that all reasonable steps have been
taken to obtain access and advise the affected property owner of the reason
for the survey and that these steps have failed.
Note: A copy of the dilapidation report is to be provided to Council
prior to any excavation works been undertaken. The dilapidation report is for
record keeping purposes only and may be used by an applicant or affected
property owner to assist in any civil action required to resolve any dispute
over damage to adjoining properties arising from works.
Reason: To record the structural condition of likely affected properties
before works commence.
10. Access through public reserve not permitted
Access for construction purposes shall not be gained
through the adjoining public reserve. Should no alternative access exist, an
application for access to the construction site via the public reserve shall
be submitted to Council for consideration and approval prior to the
commencement of works.
Reason: To protect
public reserves.
11. Construction and traffic management plan
The
applicant must submit to Council a Construction Traffic Management Plan
(CTMP), which is to be approved prior to the commencement of any works on
site.
The
plan is to consist of a report with Traffic Control Plans attached.
The
report is to contain commitments which must be followed by the excavation contractor,
builder, owner and subcontractors. The CTMP applies to all persons
associated with demolition, excavation and construction of the development.
The
report is to contain construction vehicle routes for approach and departure
to and from all directions.
The
report is to contain a site plan showing entry and exit points. Swept paths
are to be shown on the site plan showing access and egress for an 11 metre
long heavy rigid vehicle.
The
Traffic Control Plans are to be prepared by a qualified person (red card
holder). One must be provided for each of the following stages of the works:
o Excavation
o Concrete
pour
o Traffic
control for vehicles reversing into or out of the site.
Traffic
controllers must be in place at the site entry and exit points to control
heavy vehicle movements in order to maintain the safety of pedestrians and
other road users.
When
a satisfactory CTMP is received, a letter of approval will be issued with
conditions attached. Traffic management at the site must comply with the
approved CTMP as well as any conditions in the letter issued by Council.
Council’s Rangers will be patrolling the site regularly and fines may be
issued for any non-compliance with this condition.
Reason: To ensure that
appropriate measures have been considered during all phases of the
construction process in a manner that maintains the environmental amenity and
ensures the ongoing safety and protection of people.
12. Erosion and drainage management
Earthworks and/or demolition of any existing
buildings shall not commence until an erosion and sediment control plan is
submitted to and approved by the Principal Certifying Authority. The plan
shall comply with the guidelines set out in the NSW Department of Housing
manual "Managing Urban Stormwater: Soils and Construction"
certificate. Erosion and sediment control works shall be implemented in
accordance with the erosion and sediment control plan.
Reason: To preserve and
enhance the natural environment.
13. Tree fencing inspection
Upon installation of the required tree protection measures, an
inspection of the site by the Principal Certifying Authority is required to
verify that tree protection measures comply with all relevant conditions.
Reason: To protect existing trees during the construction phase.
14. Construction waste management plan
Prior to the commencement of any works, the
Principal Certifying Authority shall be satisfied that a waste management
plan, prepared by a suitably qualified person, has been prepared in
accordance with Council’s DCP 40 - Construction and Demolition Waste Management.
The plan shall address all issues identified in DCP
40, including but not limited to: the estimated volume of waste and method
for disposal for the construction and operation phases of the development.
Note: The plan shall be provided to the Certifying Authority.
Reason: To
ensure appropriate management of construction waste.
15. Noise and vibration management plan
Prior
to the commencement of any works, a noise and vibration management plan is to
be prepared by a suitably qualified expert addressing the likely noise and
vibration from demolition, excavation and construction of the proposed
development and provided to the Principal Certifying Authority. The management plan is to identify amelioration
measures to achieve the best practice objectives of AS 2436-2010 and NSW
Department of Environment and Climate Change Interim Construction Noise
Guidelines. The report shall be prepared in consultation with any
geotechnical report that itemises equipment to be used for excavation works.
The
management plan shall address, but not be limited to, the following matters:
· identification of the specific activities that will
be carried out and associated noise sources
· identification of all potentially affected sensitive
receivers, including residences, churches, commercial premises, schools and
properties containing noise sensitive equipment
· the construction noise objective specified in the
conditions of this consent
· the construction vibration criteria specified in the
conditions of this consent
· determination of appropriate noise and vibration
objectives for each identified sensitive receiver
· noise and vibration monitoring, reporting and
response procedures
· assessment of potential noise and vibration from the
proposed demolition, excavation and construction activities, including noise
from construction vehicles and any traffic diversions
· description of specific mitigation treatments,
management methods and procedures that will be implemented to control noise
and vibration during construction
· construction timetabling to minimise noise impacts
including time and duration restrictions, respite periods and frequency
· procedures for notifying residents of construction
activities that are likely to affect their amenity through noise and
vibration
· contingency plans to be implemented in the event of
non-compliances and/or noise complaints
Reason: To protect the
amenity afforded to surrounding residents during the construction process.
16. CCTV report of existing Council pipe system near works
Prior
to the commencement of any works on site, qualified practitioners must
undertake a closed circuit television inspection and then report on the
existing condition of the Council drainage pipeline through Lots 8 to 14. The
report must be provided to Council’s, Development Engineer and is to include
a copy of the video footage of the pipeline. A written acknowledgment from
Council’s Development Engineer (attesting to this condition being
appropriately satisfied) shall be obtained and submitted to the Principal
Certifying Authority prior to the commencement of any works on site.
Reason: To protect
Council’s infrastructure.
Conditions to be satisfied prior to the issue of the construction
certificate:
17. Project ecologist
A Project Ecologist shall be commissioned prior to the release
of the Construction Certificate to ensure all bushland/environmental
protection measures are carried out in accordance with the conditions of
consent.
The Project Ecologist shall have a minimum qualification of TAFE
Certificate III in Bush Regeneration or Conservation and Land Management -
Natural Area Restoration. He/she shall have at least 4 years experience in
the management of native bushland in the Sydney region. Details of the
arborist including name, business name and contact details shall be provided
to the Principal Certifying Authority with a copy to Council.
Reason: To ensure the protection of existing biodiversity values of
the site
18. Fauna protection
Prior to works commencing and/or tree removal works a qualified
ecologist shall investigate all trees within the development for fauna
occupation. In accordance with appropriate licensing requirements the
ecologist shall supervise the relocation of any fauna found within the trees
approved for removal.
The qualified ecologist must hold an Animal Ethics Permit from
the Office of Environment & Heritage and a wildlife licence under section
132C of the National Parks and Wildlife Act 1974 issued by the Office of
Environment and Heritage.
Evidence of engagement of the qualified ecologist and the
required licensing must be provided to the Private Certifying Authority with
a copy to Council prior to the trees being removed.
Reason: To ensure protection of fauna
species.
19. Nest boxes
Prior to works commencing and/or tree
removal works being undertaken eighteen nest boxes comprising of 6 small
mammal & 6 medium mammal, 6 microbat boxes shall be installed within the
retained (bushland) area to the south of the proposed development. The nest
boxes shall be constructed of durable wood material (marine ply) and
installed at a minimum height of 6 metres from the ground and positioned
under the direction of a qualified ecologist.
The qualified ecologist must hold an Animal Ethics
Permit from the Office of Environment & Heritage and a wildlife licence
under section 132C of the National Parks and Wildlife Act 1974 issued
by the Office of Environment and Heritage.
Reason: To ensure protection of fauna species.
20. Amendments to approved tree protection plan
Prior to the issue of a Construction Certificate, the Principal
Certifying Authority shall be satisfied that the approved tree protection
plans, listed below and endorsed with Council’s stamp, have been amended in
accordance with the requirements of this condition as well as other
conditions of this consent:
|
Plan no.
|
Drawn by
|
Date
|
|
TMP01
Sheets 1- 2 Rev B
|
Naturally
Trees
|
8/04/15
|
The above tree protection plan(s) shall be amended in the
following ways:
1. Tree protection and ground protection is to be provided to
the bushland edge directly southeast of the proposed access road, retaining
wall to Lot 14 and stormwater works. The fencing is to connect to that shown
in association with Trees 830 and 831. Sediment fencing is to be relocated
along the line of the tree protection fencing.
Note: An
amended plan, prepared by a qualified arborist and verified by the Project
Arborist and Project Ecologist shall be submitted to the Certifying
Authority.
Reason : To protect existing trees during construction phase
21. Long service levy
In
accordance with Section 109F(i) of the Environmental Planning and Assessment
Act a Construction Certificate shall not be issued until any long service
levy payable under Section 34 of the Building and Construction Industry Long
Service Payments Act 1986 (or where such levy is payable by instalments, the
first instalment of the levy) has been paid. Council is authorised to accept
payment. Where payment has been made elsewhere, proof of payment is to be provided
to Council.
Reason: Statutory requirement.
22. Builder’s indemnity insurance
The applicant, builder, developer or person who does
the work on this development, must arrange builder’s indemnity insurance and
submit the certificate of insurance in accordance with the requirements of
Part 6 of the Home Building Act 1989 to the Certifying Authority for
endorsement of the plans accompanying the Construction Certificate.
It is the responsibility of the applicant, builder
or developer to arrange the builder's indemnity insurance for residential
building work over the value of $20,000. The builder's indemnity insurance
does not apply to commercial or industrial building work or to residential
work valued at less than $20,000, nor to work undertaken by persons holding
an owner/builder's permit issued by the Department of Fair Trading (unless
the owner/builder's property is sold within 7 years of the commencement of
the work).
Reason: Statutory requirement.
23. Outdoor lighting
Prior
to the issue of a Construction Certificate, the Certifying Authority shall be
satisfied that all outdoor lighting will comply with AS/NZ1158.3: 1999
Pedestrian Area (Category P) Lighting and AS4282: 1997 Control of the
Obtrusive Effects of Outdoor Lighting.
Note: Details demonstrating
compliance with these requirements are to be submitted prior to the issue of
a Construction Certificate.
Reason: To provide high
quality external lighting for security without adverse affects on public
amenity from excessive illumination levels.
24. Tree protection fencing/ground protection
To preserve the following tree/s, no work shall commence until
the area beneath their canopy is fenced off or ground protection installed as
per following Tree Management Plans to prevent any activities, storage or the
disposal of materials within the fenced area. The fencing/ground protection
shall be maintained intact until the completion of all demolition/building
work on site.
|
Plan no.
|
Drawn by
|
Date
|
|
TMP01
Sheets 1- 2 Rev B
|
Naturally
Trees
|
8/04/15
|
The tree protection fencing shall be constructed of galvanised
pipe at 2.4 metre spacings and connected by securely attached chain mesh
fencing to a minimum height of 1.8 metres in height prior to work commencing.
Ground protection shall be in accordance with AS4970-2009 Protection of trees
on development sites.
Reason : To protect existing trees during construction phase
25. Design of works in public road (Roads Act approval)
If
the design for the new Council pipe from Eton Road to the bioretention basin
has not been approved with the Council report, then prior to issue of the
Construction Certificate, the Certifying Authority shall be satisfied that
engineering plans and specifications prepared by a qualified consulting
engineer have been approved by Council’s Development Engineer. The plans to
be assessed must be to a detail suitable for construction issue purposes
Development
consent does not give approval to these works on Council's asset. The
applicant must obtain a separate approval under sections 138 and 139 of The
Roads Act 1993 for the works required as part of the development. The
Construction Certificate must not be issued, and these works must not proceed
until Council has issued a formal written approval under the Roads Act 1993.
The
required plans and specifications are to be designed in accordance with the
General Specification for the Construction of Road and Drainage Works in
Ku-ring-gai Council, dated November 2004. The drawings must detail existing
utility services and trees affected by the works, erosion control
requirements and traffic management requirements during the course of works.
Survey must be undertaken as required. Traffic management is to be certified
on the drawings as being in accordance with the documents SAA HB81.1 - 1996 -
Field Guide for Traffic Control at Works on Roads - Part 1 and RTA Traffic
Control at Work Sites (1998). Construction of the works must proceed only in
accordance with any conditions attached to the Roads Act approval issued by
Council.
A
minimum of three (3) weeks will be required for Council to assess the Roads
Act application. Early submission of the Roads Act application is recommended
to avoid delays in obtaining a Construction Certificate. An engineering
assessment and inspection fee (set out in Council’s adopted fees and charges)
is payable and Council will withhold any consent and approved plans until
full payment of the correct fees. Plans and specifications must be marked to
the attention of Council’s Development Engineers. In addition, a copy of this
condition must be provided, together with a covering letter stating the full
address of the property and the accompanying DA number.
Reason: To ensure that the plans are suitable for construction purposes.
26. Utility provider requirements
Prior
to issue of the Construction Certificate, the applicant must make contact
with all relevant utility providers whose services will be impacted upon by
the development. A written copy of the requirements of each provider, as
determined necessary by the Certifying Authority, must be obtained. All
utility services or appropriate conduits for the same must be provided by the
developer in accordance with the specifications of the utility providers.
Reason: To ensure compliance with the requirements of relevant utility
providers.
27. Underground services
All
electrical services (existing and proposed) shall be undergrounded from the
proposed building on the site to the appropriate power pole(s) or other
connection point. Undergrounding of services must not disturb the root system
of existing trees and shall be undertaken in accordance with the requirements
of the relevant service provided. Documentary evidence that the relevant
service provider has been consulted and that their requirements have been met
are to be provided to the Certifying Authority prior to the issue of the
Construction Certificate. All electrical and telephone services to the
subject property must be placed underground and any redundant poles are to be
removed at the expense of the applicant.
Reason: To provide
infrastructure that facilitates the future improvement of the streetscape by
relocation of overhead lines below ground.
Conditions to be satisfied prior to the issue of the construction
certificate or prior to demolition, excavation or construction
(whichever comes first):
28. Infrastructure restorations fee
To
ensure that damage to Council Property as a result of construction activity
is rectified in a timely matter:
a) All work or activity taken in
furtherance of the development the subject of this approval must be
undertaken in a manner to avoid damage to Council Property and must
not jeopardise the safety of any person using or occupying the adjacent
public areas.
b) The applicant, builder,
developer or any person acting in reliance on this approval shall be
responsible for making good any damage to Council Property, and for the
removal from Council Property of any waste bin, building materials, sediment,
silt, or any other material or article.
c) The Infrastructure Restoration
Fee must be paid to the Council by the applicant prior to both the issue of
the Construction Certificate and the commencement of any earthworks or
construction.
d) In consideration of payment of
the Infrastructure Restorations Fee, Council will undertake such inspections
of Council Property as Council considers necessary and also undertake, on
behalf of the applicant, such restoration work to Council Property, if any,
that Council considers necessary as a consequence of the development. The
provision of such restoration work by the Council does not absolve any person
of the responsibilities contained in (a) to (b) above. Restoration work to be
undertaken by the Council referred to in this condition is limited to work hat
can be undertaken by Council at a cost of not more than the Infrastructure
Restorations Fee payable pursuant to this condition.
e) In
this condition:
“Council Property” includes any
road, footway, footpath paving, kerbing, guttering, crossings, street
furniture, seats, letter bins, trees, shrubs, lawns, mounds, bushland,
and similar structures or features on any road or public road within the
meaning of the Local Government Act 1993 (NSW) or any public place; and
“Infrastructure Restoration
Fee” means the Infrastructure Restorations Fee calculated in accordance with
the Schedule of Fees & Charges adopted by Council as at the date of
payment and the cost of any inspections required by the Council of Council
Property associated with this condition.
Reason: To maintain
public infrastructure.
29. Bush fire risk certification
Bush fire protection measures shall be carried out in accordance
with the following bush fire risk assessment, report and certificate, listed
below and endorsed with Council’s stamp, except where amended by other
conditions of this consent:
|
Document title
|
Prepared by
|
Dated
|
|
Bushfire Protection
Assessment
|
Ecological Australia
|
October 2014
|
Prior to the issue of the construction certificate, the
principal certifying authority must be satisfied that the construction
certificate is in accordance with the recommendations of the report and
certificate as listed above.
Reason: To ensure that the development is in accordance with the
determination.
Conditions to be satisfied during the demolition, excavation and
construction phases:
30. Road
opening permit
The opening of
any footway, roadway, road shoulder or any part of the road reserve shall not
be carried out without a road opening permit being obtained from Council
(upon payment of the required fee) beforehand.
Reason: Statutory requirement (Roads Act 1993
Section 138) and to maintain the integrity of Council’s infrastructure.
31. Prescribed conditions
The
applicant shall comply with any relevant prescribed conditions of development
consent under clause 98 of the Environmental Planning and Assessment
Regulation. For the purposes of section 80A (11) of the Environmental
Planning and Assessment Act, the following conditions are prescribed in
relation to a development consent for development that involves any building
work:
· The work must be carried out in accordance with the
requirements of the Building Code of Australia
· In the case of residential building work for which
the Home Building Act 1989 requires there to be a contract of
insurance in force in accordance with Part 6 of that Act, that such a
contract of insurance is in force before any works commence.
Reason: Statutory
requirement.
32. Hours of work
Demolition,
excavation, construction work and deliveries of building material and
equipment must not take place outside the hours of 7.00am to 5.00pm Monday to
Friday and 8.00am to 12 noon Saturday. No work and no deliveries are to take
place on Sundays and public holidays.
Excavation
or removal of any materials using machinery of any kind, including
compressors and jack hammers, must be limited to between 7.30am and 5.00pm
Monday to Friday, with a respite break of 45 minutes between 12 noon 1.00pm.
Where
it is necessary for works to occur outside of these hours (ie) placement of
concrete for large floor areas on large residential/commercial developments
or where building processes require the use of oversized trucks and/or cranes
that are restricted by the RTA from travelling during daylight hours to
deliver, erect or remove machinery, tower cranes, pre-cast panels, beams,
tanks or service equipment to or from the site, approval for such activities
will be subject to the issue of an "outside of hours works permit"
from Council as well as notification of the surrounding properties likely to
be affected by the proposed works.
Note: Failure to obtain a permit to work outside
of the approved hours will result in on the spot fines being issued.
Reason: To ensure reasonable standards of amenity for
occupants of neighbouring properties.
33. Rural Fire Service conditions
Asset Protection Zones
The intent of measures is to provide sufficient
space and maintain reduced fuel loads so as to ensure radiant heat levels of
buildings are below critical limits and to prevent direct flame contact with
a building. To achieve this, the following conditions shall apply:
1. At the commencement of building works, and in
perpetuity, the site shall be managed as an Inner Protection Area (IPA) as
outlined within section 4.1.3 and Appendix 5 of 'Planning for Bush Fire
Protection 2006' and the NSW Rural Fire Service's document 'Standards for
asset protection zones'.
Water and utilities
The intent of measures is to provide adequate services
of water for the protection of buildings during and after the passage of a
bush fire, and to locate gas and electricity so as not to contribute to the
risk of fire to a building. To achieve this, the following conditions shall
apply:
2. The provision of water, electricity and gas shall
comply with section 4.1.3 of 'Planning for Bush Fire Protection 2006'.
Access
The intent of measures for property access is to
provide safe access to/from the public road system for fire fighters
providing property protection during a bush fire and for occupants faced with
evacuation. To achieve this, the following conditions shall apply:
3. The proposed shared property access road shall
comply with section 4.1.3 (2) of ‘Planning for Bush Fire Protection 2006’.
Design and construction
The intent of measures is that buildings are
designed and constructed to withstand the potential impacts of bush fire
attack. To achieve this, the following conditions shall apply:
4. The north-east, south-east and south-west
elevations of dwellings proposed on lots 11-14 (as shown on drawing no.
P5_DA02.001[1], prepared by BatesSmart, revision 1, dated 26/9/2014) shall
comply with section 3 and section 7 (BAL 29) Australian Standard AS3959-2009
‘Construction of buildings in bush fire-prone areas’ and section A3.7
Addendum Appendix 3 of 'Planning for Bush Fire Protection' 2006’.
5. The north-west elevations of dwellings proposed
on lots 11-14 and north-east and south-east elevations of dwellings proposed
on lots 8-10 (as shown on drawing no. P5_DA02.001[1], prepared by BatesSmart,
revision 1, dated 26/9/2014) shall comply with section 3 and section 6 (BAL
19) Australian Standard AS3959-2009 ‘Construction of buildings in bush
fire-prone area’ and section A3.7 Addendum Appendix 3 of 'Planning for Bush
Fire Protection' 2006’.
6. The south-west and north-west elevations of
dwellings proposed on lots 8-10 and all elevations of dwellings proposed on
lots 2 to 7 (as shown on drawing no. P5_DA02.001[1], prepared by BatesSmart,
revision 1, dated 26/9/2014) shall comply with Sections 3 and 5 (BAL 12.5)
Australian Standard AS3959-2009 'Construction of buildings in bush fire-prone
areas' and section A3.7 Addendum Appendix 3 of 'Planning for Bush Fire
Protection 2006'.
Reason: statutory requirement
34. Temporary
irrigation
Temporary irrigation within
the Tree protection fencing is to be provided where necessary during all
stages of works. Irrigation volumes are to be determined by the Project
Arborist.
Reason: To protect
trees to be retained on site.
35. Demolition
of existing site structures
To preserve the health and
condition of existing trees to be retained, all demolition of existing
structures including tree removal, are to be undertaken within the access
restricted to the existing roads and in accordance with Section 2, Appendix 6
and Appendix 7, Arboricultural Impact Appraisal and Method Statement, Naturally Trees, 8/04/15(Rev
B). Where vehicular access is required across existing soft landscape
area, temporary ground protection capable of supporting the vehicles is to be
constructed in accordance with
Section 4.5.3, AS4970-2009 Protection of trees on development sites.
Reason: To protect
trees to be retained on site.
36. Approved plans to be on site
A copy of all approved and certified plans, specifications and
documents incorporating conditions of consent and certification (including
the Construction Certificate if required for the work) shall be kept on site
at all times during the demolition, excavation and construction phases and
must be readily available to any officer of Council or the Principal
Certifying Authority.
Reason: To ensure that the development is in accordance with the
determination.
37. Engineering fees
For
the purpose of any development related inspections by Ku-ring-gai Council
engineers, the corresponding fees set out in Councils adopted Schedule of
Fees and Charges are payable to Council. A re-inspection fee per visit may be
charged where work is unprepared at the requested time of inspection, or
where remedial work is unsatisfactory and a further inspection is required.
Engineering fees must be paid in full prior to any final consent from
Council.
Reason: To protect
public infrastructure.
38. Construction noise
During
excavation, demolition and construction phases, noise generated from the site
shall be controlled in accordance with the recommendations of the approved
noise and vibration management plan.
Reason: To ensure
reasonable standards of amenity to neighbouring properties.
39. Site notice
A
site notice shall be erected on the site prior to any work commencing and
shall be displayed throughout the works period.
The
site notice must:
·
be prominently displayed at the
boundaries of the site for the purposes of informing the public that
unauthorised entry to the site is not permitted
·
display project details
including, but not limited to the details of the builder, Principal
Certifying Authority and structural engineer be durable and weatherproof
·
display the approved hours of
work, the name of the site/project manager, the responsible managing company
(if any), its address and 24 hour contact phone number for any inquiries,
including construction/noise complaint are to be displayed on the site notice
·
be mounted at eye level on the
perimeter hoardings/fencing and is to state that unauthorised entry to the
site is not permitted
Reason: To ensure public
safety and public information.
40. Dust control
During
excavation, demolition and construction, adequate measures shall be taken to
prevent dust from affecting the amenity of the neighbourhood. The following
measures must be adopted:
·
physical barriers shall be
erected at right angles to the prevailing wind direction or shall be placed
around or over dust sources to prevent wind or activity from generating dust
·
earthworks and scheduling
activities shall be managed to coincide with the next stage of development to
minimise the amount of time the site is left cut or exposed
·
all materials shall be stored or
stockpiled at the best locations
·
the ground surface should be
dampened slightly to prevent dust from becoming airborne but should not be
wet to the extent that run-off occurs
·
all vehicles carrying spoil or
rubble to or from the site shall at all times be covered to prevent the
escape of dust
·
all equipment wheels shall be
washed before exiting the site using manual or automated sprayers and
drive-through washing bays
·
gates shall be closed between
vehicle movements and shall be fitted with shade cloth
·
cleaning of footpaths and
roadways shall be carried out daily
Reason: To protect the
environment and amenity of surrounding properties.
41. Post-construction dilapidation report
The
applicant shall engage a suitably qualified person to prepare a post
construction dilapidation report at the completion of the construction works.
This report is to ascertain whether the construction works created any
structural damage to adjoining buildings, infrastructure and roads. The
report is to be submitted to the Principal Certifying Authority. In
ascertaining whether adverse structural damage has occurred to adjoining
buildings, infrastructure and roads, the Principal Certifying Authority must:
·
compare the post-construction
dilapidation report with the pre-construction dilapidation report
·
have written confirmation from
the relevant authority that there is no adverse structural damage to their
infrastructure and roads.
A
copy of this report is to be forwarded to Council at the completion of the
construction works.
Reason: Management of
records.
42. Use of road or footpath
During excavation, demolition and construction
phases, no building materials, plant or the like are to be stored on the road
or footpath without written approval being obtained from Council beforehand.
The pathway shall be kept in a clean, tidy and safe condition during building
operations. Council reserves the right, without notice, to rectify any such
breach and to charge the cost against the applicant/owner/builder, as the
case may be.
Reason: To ensure safety
and amenity of the area.
43. Guarding excavations
All excavation, demolition and construction works
shall be properly guarded and protected with hoardings or fencing to prevent
them from being dangerous to life and property.
Reason: To ensure public
safety.
44. Toilet facilities
During excavation, demolition and construction
phases, toilet facilities are to be provided, on the work site, at the rate
of one toilet for every 20 persons or part of 20 persons employed at the
site.
Reason: Statutory
requirement.
45. Certification of footings & excavation adjacent to
easements
During
demolition and construction, the Principal Certifying Authority shall be
satisfied that:
·
footings, and any required
permanent excavation or drainage easement support, are constructed in
accordance with the conditions of this consent relating to footings and
excavation adjacent to drainage easements and/or drainage pipes
·
footings allow for complete
future excavation over the full width of the easement to a depth of the
invert of the pipe, without the need to support or underpin the subject
structure
Reason: Safety.
46. Recycling of building material (general)
During
demolition and construction, the Principal Certifying Authority shall be
satisfied that building materials suitable for recycling have been forwarded
to an appropriate registered business dealing in recycling of materials.
Materials to be recycled must be kept in good order.
Reason: To facilitate
recycling of materials.
47. Maintenance period for works on Council asset
A
maintenance period of six (6) months applies to all work on Council's assets
carried out by the applicant - after the works have been completed to the
satisfaction of Ku-ring-gai Council. In that maintenance period, the applicant
shall be liable for any section of the public infrastructure work which fails
to perform in the designed manner, or as would reasonably be expected under
the operating conditions. The maintenance period shall commence once the
applicant receives a formal letter from Council stating that the works
involving public infrastructure have been completed satisfactorily.
Reason: To protect
public infrastructure.
48. Road reserve safety
All
public footways and roadways fronting and adjacent to the site must be
maintained in a safe condition at all times during the course of the
development works. Construction materials must not be stored in the road
reserve. A safe pedestrian circulation route and a pavement/route free of
trip hazards must be maintained at all times on or adjacent to any public
access ways fronting the construction site. Where public infrastructure is
damaged, repair works must be carried out when and as directed by Council
officers. Where pedestrian circulation is diverted on to the roadway or verge
areas, clear directional signage and protective barricades must be installed
in accordance with AS1742-3 (1996) “Traffic Control Devices for Work on
Roads”. If pedestrian circulation is not satisfactorily maintained across the
site frontage, and action is not taken promptly to rectify the defects,
Council may undertake proceedings to stop work.
Reason: To ensure safe
public footways and roadways during construction.
49. Services
Where
required, the adjustment or inclusion of any new utility service facilities
must be carried out by the applicant and in accordance with the requirements
of the relevant utility authority. These works shall be at no cost to
Council. It is the applicants’ full responsibility to make contact with the
relevant utility authorities to ascertain the impacts of the proposal upon
utility services (including water, phone, gas and the like). Council accepts
no responsibility for any matter arising from its approval to this
application involving any influence upon utility services provided by another
authority.
Reason: Provision of
utility services.
50. Footings and excavation near easements
Footings
to be located adjacent to easements and/or Council drainage pipes shall be
sited and constructed so that all footings are located outside of easement
boundaries.
The
applicant shall refer to Council Plan 80-011 concerning such works. Footings
must extend to at least the depth of the invert of the adjacent pipe within
the easement unless the footings are to be placed on competent bedrock. If
there is no pipe within the easement, a future depth of pipe of 1.6 metres is
to be assumed for future pipe placement. If there is a Council pipe without
an easement a future easement width of 1.8 metres centred on the pipeline is
to be adopted.
If
permanent excavation is proposed beneath the obvert of the pipe within the
easement, suitable means to protect the excavation from seepage or other
water flow from the pipe and trench and means to retain the easement and
associated pipe cover are to be provided at no cost to Council. Council
accepts no liability for such seepage or water flows now or at any time in
the future resulting from such excavation.
Reason: To ensure
structural stability.
51. Structures to be clear of drainage easements
During
all phases of demolition, excavation and construction, it is the full
responsibility of the applicant and their contractors to:
·
ascertain the exact location of
the Council drainage pipe traversing the site in the vicinity of the
works
·
take full measures to protect
the in-ground Council drainage system
·
ensure dedicated overland flow
paths are satisfactorily maintained through the site
Drainage
pipes can be damaged through applying excessive loading (such as construction
machinery, material storage and the like). All proposed structures and
construction activities are to be sited fully clear of Council drainage pipes,
drainage easements, watercourses and trunk overland flow paths on the site.
Trunk or dedicated overland flow paths must not be impeded or diverted by
fill or structures unless otherwise approved.
If
a Council drainage pipeline is uncovered during construction, all work is to
cease and the Principal Certifying Authority and Council must be contacted
immediately for advice. Any damage caused to a Council drainage system must
be immediately repaired in full as directed and at no cost to Council.
Reason: To protect existing Council infrastructure and
maintain over land flow paths.
52. Sydney Water Section 73 Compliance Certificate
The
applicant must obtain a Section 73 Compliance Certificate under the Sydney
Water Act 1994. An application must be made through an authorised Water
Servicing CoOrdinator. The applicant is to refer to “Your Business” section
of Sydney Water’s web site at www.sydneywater.com.au
<http://www.sydneywater.com.au> then the “e-develop” icon or
telephone 13 20 92. Following application a “Notice of Requirements” will
detail water and sewer extensions to be built and charges to be paid. Please
make early contact with the CoOrdinator, since building of water/sewer
extensions can be time consuming and may impact on other services and
building, driveway or landscape design.
Reason: Statutory
requirement.
53. Arborist’s
report
The
trees to be retained shall be inspected, monitored and treated by a Project
Arborist who must be a qualified (AQF) Level 5 arborist in accordance with
AS4970-2009 Protection of trees on development sites. Regular inspections
and documentation from the Project Arborist to the Principal Certifying
Authority are required including at the following times or phases of work.
All monitoring shall be recorded and provided to the Principal Certifying
Authority prior to completion of the works.
|
Schedule
|
|
Tree/location
|
Time
of inspection
|
|
As shown on Tree Management Plan, Naturally Trees, 15/04/14
|
As
per Programme of arboricultural input, Appendix 7, Arboricultural
Impact Appraisal and Method Statement, Naturally Trees, 15/04/14.
|
Reason: To ensure protection of existing trees.
54. Treatment of tree roots
If tree roots are required to be severed for the purposes of
constructing the approved works, they shall be cut cleanly by hand, by an
experienced Arborist/Horticulturist with a minimum qualification of
Horticulture Certificate or Tree Surgery Certificate. All pruning works
shall be undertaken as specified in Australian Standard 4373-2007 - Pruning
of Amenity Trees.
Reason: To protect existing trees.
55. No storage of materials beneath trees
No activities, storage or disposal of materials shall take place
beneath the canopy of any tree protected under Council's Tree Preservation
Order at any time.
Reason: To protect existing trees.
56. Removal of refuse
All builders' refuse, spoil and/or material unsuitable for use
in landscape areas shall be removed from the site on completion of the
building works.
Reason: To protect the environment.
57. On site retention of waste dockets
All demolition, excavation and construction waste
dockets are to be retained on site, or at suitable location, in order to
confirm which facility received materials generated from the site for recycling
or disposal.
· Each
docket is to be an official receipt from a facility authorised to accept the material
type, for disposal or processing.
· This
information is to be made available at the request of an Authorised Officer
of Council.
Reason: To protect the environment.
Conditions to be satisfied prior to the issue of an Occupation
Certificate:
58. Concept approval
All
works associated with the development and its ongoing use shall have regard
to, and be undertaken in accordance with the Conditions and supporting
documentation of Concept Approval MP06_0130.
Reason: To ensure
compliance with the Concept Approval.
59. Positive covenant and easement over bioretention basin
Prior
to the issue of an Occupation Certificate, the Principal Certifying Authority
is to be satisfied that an easement or equivalent has been created over the
bioretention basin in terms which allow its maintenance by the community
association together with a positive covenant and restriction on use
describing how it is to be maintained. The terms of the positive covenant
and restriction on use can be generally in accordance with Council's
"draft terms of Section 88B Instrument for the protection of on site
detention facilities".
Reason: To protect the
environment.
60. Compliance with BASIX Certificate
Prior
to the issue of an Occupation Certificate, the Principal Certifying Authority
shall be satisfied that all commitments listed in BASIX Certificate No.
577084M have been complied with.
Reason: Statutory
requirement.
61. Completion of landscape works
Prior to the release of the Occupation Certificate, the
Principal Certifying Authority is to be satisfied that all landscape works,
including the removal of all noxious and/or environmental weed species, have
been undertaken in accordance with the approved plan(s) and conditions of
consent.
Reason: To ensure that the landscape works are consistent
with the development consent.
62. Completion of tree works
Prior to the release of the Occupation Certificate, the Principal
Certifying Authority is to be satisfied that all tree works, including
pruning in accordance with AS4373-2007 or remediation works in accordance
with AS4370-2009, have been undertaken in accordance with the approved
plan(s) and conditions of consent.
Reason: To ensure that the tree works are
consistent with the development consent.
63. Retention and re-use positive covenant
Prior
to issue of the Final Occupation Certificate, the applicant must create a
positive covenant and restriction on the use of land under Section 88B or 88E
of the Conveyancing Act 1919, burdening the property with the requirement to
maintain the site stormwater retention and re-use facilities and water
quality measures (such as rain-gardens) on the property.
The
terms of the instruments are to be generally in accordance with the Council's
"draft terms of Section 88B instruments for protection of retention and
re-use facilities" and to the satisfaction of Council (refer to
appendices of Ku-ring-gai Water Management Development Control Plan No. 47).
For existing titles, the positive covenant and the restriction on the use of
land is to be created through an application to the Land Titles Office in the
form of a request using forms 13PC and 13RPA. The relative location of the
reuse and retention facility, in relation to the building footprint, must be
shown on a scale sketch, attached as an annexure to the request forms.
Registered
title documents showing the covenants and restrictions must be submitted to
and approved by the Principal Certifying Authority prior to issue of the
Final Occupation Certificate.
Reason: To protect the
environment.
64. Certification of drainage and roadworks
Prior
to issue of the Occupation Certificate, the Principal Certifying Authority is
to be satisfied that the stormwater drainage and roadworks have been
satisfactorily completed in accordance with the approved Construction
Certificate drainage plans.
Note:
A suitably qualified engineer is to provide evidence documenting the above.
Reason: To protect the
environment.
65. WAE plans
Prior
to issue of the Occupation Certificate, a registered surveyor must provide a
works as executed survey of the completed stormwater drainage and management
systems and the new road and retaining structures. The survey must be
submitted to and approved by the Principal Certifying Authority prior to
issue of the Occupation Certificate. The survey must indicate:
·
as built (reduced) surface and
invert levels for all drainage pits
·
gradients of drainage lines,
materials and dimensions
·
as built (reduced) level(s) at
the approved point of discharge to the public drainage system
·
as built location and internal
dimensions of all detention and retention structures on the property (in plan
view) and horizontal distances to nearest adjacent boundaries and structures
on site
·
the achieved storage volumes of
the installed retention and detention storages and derivative calculations
·
as built locations of all access
pits and grates in the detention and retention system(s), including
dimensions
·
the size of the orifice or
control fitted to any on-site detention system
·
dimensions of the discharge
control pit and access grates
·
the maximum depth of storage
possible over the outlet control
·
top water levels of storage
areas and indicative RL’s through the overland flow path in the event of
blockage of the on-site detention system
The
works as executed plan(s) must show the as built details above in comparison
to those shown on the drainage plans approved with the Construction
Certificate prior to commencement of works. All relevant levels and details
indicated must be marked in red on a copy of the Principal Certifying
Authority stamped construction certificate stormwater plans.
Reason: To protect the
environment.
66. CCTV report of pipe after work
Prior
to issue of the Occupation Certificate, a closed circuit television
inspection and report on the Council drainage pipeline traversing the site is
to be undertaken by appropriate contractors and provided to Council’s
Development Engineer. The report is to include a copy of the footage of the
inside of the pipeline. Any damage that has occurred to the section of the
pipeline since the commencement of construction on the site must be repaired
in full to the satisfaction of Council’s Development Engineer at no cost to
Council.
Reason: To protect the
environment.
67. Sydney Water Section 73 Compliance Certificate
Prior
to issue of an Occupation Certificate the Section 73 Sydney water Compliance
Certificate must be obtained and submitted to the Principal Certifying
Authority
Reason: Statutory
requirement.
68. Construction of infrastructure works - approved plans
Prior
to issue of the Occupation Certificate, the Principal Certifying Authority
must be satisfied that all approved drainage works have been completed in
accordance with the Council Roads Act approval and accompanying drawings,
conditions and specifications.
The
works must be supervised by the applicant’s designing engineer and completed
and approved to the satisfaction of Ku-ring-gai Council.
The
supervising consulting engineer is to provide certification upon completion
that the works were constructed in accordance with the Council approved
stamped drawings. The works must be subject to inspections by Council at the
hold points noted on the Roads Act approval. All conditions attached to the
approved drawings for these works must be met prior to the Occupation
Certificate being issued.
Reason: To ensure that
works undertaken on Council's assets are to the satisfaction of Council.
69. Infrastructure repair
Prior
to issue of the Occupation Certificate, the Principal Certifying Authority
must be satisfied that any damaged public infrastructure caused as a result
of construction works (including damage caused by, but not limited to,
delivery vehicles, waste collection, contractors, sub-contractors, concrete
vehicles) is fully repaired to the satisfaction of Council Development
Engineer and at no cost to Council.
Reason: To protect
public infrastructure.
Conditions to be satisfied prior to the issue of a Subdivision
certificate:
70. Easement for waste collection
An
easement for waste collection is to be created under Section 88B of the
Conveyancing Act 1919. This is to permit legal access for Council, Council’s
contractors and their vehicles over the subject property for the purpose of
collecting waste from the property. The terms of the easement are to be
generally in accordance with Council’s draft terms for an easement for waste
collection and shall be to the satisfaction of Council’s Development
Engineer.
Reason: To permit legal access for Council, Council’s
contractors and their vehicles over the subject site for waste collection.
71. Sydney Water Section 73 Compliance Certificate
Prior
to release of the linen plan/issue of the subdivision certificate, the
Section 73 Sydney Water compliance certificate which refers to the
subdivision application must be obtained and submitted to the Council.
Reason: Statutory
requirement.
72. Requirements of public authorities for connection to services
Prior
to the issue of the Subdivision Certificate, the Principal Certifying
Authority shall be satisfied that the applicant has complied with the
requirements of any public authorities (e.g. Energy Australia, Sydney Water,
Telstra Australia, AGL, etc) in regard to the connection, relocation and/or
adjustment of the services affected by the proposed subdivision. All costs
related to the relocation, adjustment or support of services are the responsibility
of the applicant.
Note: Details of compliance with the requirements
of any relevant public authorities are to be submitted to the Principal
Certifying Authority.
Reason: To ensure that
services are available to the allotments of land.
73. Provision of services
Prior
to issue of the Subdivision Certificate, separate underground electricity,
gas and phone or appropriate conduits for the same, must be provided to each
allotment to the satisfaction of the utility provider. A suitably qualified
and experienced engineer or surveyor is to provide certification that all new
lots have ready underground access to the services of electricity, gas and
phone. Alternatively, a letter from the relevant supply authorities stating
the same may be submitted to satisfy this condition.
Reason: Access to public
utilities.
74. Submission of 88b instrument
Prior
to the issue of the Subdivision Certificate, the applicant must submit an
original instrument under Section 88B of the Conveyancing Act with the plan
of subdivision, plus six (6) copies to Council. Ku-ring-gai Council must be
named as the authority whose consent is required to release, vary or modify
the burdens.
Reason: To create all required easements,
rights-of-carriageway, positive covenants, restrictions-on-use or other
burdens/benefits as may be required.
75. Submission of plans of subdivision
For
endorsement of the subdivision certificate, the applicant shall submit an
original plan of subdivision plus 6 copies, suitable for endorsement by
Council. The following details must be submitted with the plan of subdivision
and its copies:
a) the
endorsement fee current at the time of lodgement
b) the
88B instrument plus 6 copies
c) all
surveyor’s and/or consulting engineers’ certification(s) required under this subdivision
consent
d) The
Section 73 (Sydney Water) Compliance Certificate for the subdivision.
e) The
Precinct Plan
Council
will check the consent conditions on the subdivision. Failure to submit the
required information will delay endorsement of the linen plan and may require
payment of rechecking fees. Plans and copies of subdivision must not be
folded. Council will not accept bonds in lieu of completing subdivision
works.
Reason: Statutory
requirement.
76. General easement/R.O.W. provision and certification
Prior
to issue of the Subdivision Certificate, a registered surveyor is to provide
details to Council that all physical structures are fully contained within
the proposed allotments or will be fully covered by the proposed burdens upon
registration of the final plan of subdivision. Alternatively, where the
surveyor is of the opinion that creation of burdens and benefits is not
required, then proof to this effect must be submitted to the Principal
Certifying Authority.
Reason: To ensure that all physical structures are fully
contained within the proposed allotments or will be fully covered by the
proposed burdens upon registration of the final plan of subdivision.
CARRIED
UNANIMOUSLY
|